Infrastructure Intelligence No. 13: From Power Consumption to Power Participation

Energy. Power. Development. Capital. | November 24, 2026 | Issue No. 13
THE WEEK IN INFRASTRUCTURE
Large Customers Move Into the Infrastructure Stack
The Senate passed the Bipartisan American Affordability and Jobs Act 62–33 on November 19. The House must now pass the same text before it can become law.
Large electricity customers moved further into financing the grid. Google offered to pay $10.8 million to upgrade transmission lines in Columbus. FERC cleared a structure that lets NIPSCO buy power for its data-center customers from an affiliate built to serve them.
Avantus signed $3 billion of solar and storage contracts with PG&E, which still need state approval. FERC certificated five gas projects, including a pipeline expansion contracted to a new Entergy Mississippi power plant. DigitalBridge cleared FERC review of its ArcLight acquisition.
ERCOT's Batch Zero remains paused ahead of two reports due December 10. New Section 232 minimum import prices for solar take effect December 4.
The thread running through the week: customers are no longer only waiting for capacity. Increasingly, they are paying to create it.
01 | THE LEAD
Senate Passes Permitting Reform; the House Decides Next
On November 19, the Senate voted 62–33 to pass the Bipartisan American Affordability and Jobs Act. Support came from 47 Republicans, 14 Democrats and one independent. Thirty Democrats, two Republicans and one independent opposed it.
It was final Senate passage. It follows the November 9 vote to begin debate, the Lead in Issue No. 11, and the November 16 vote on the managers' amendment, covered in Issue No. 12. The bill was introduced as S. 5653, first covered in Issue No. 07. The Senate passed it as an amendment to H.R. 2347, a bill the House had already passed. The House must now agree to the Senate's text.
According to the Bipartisan Policy Center's summary, the Senate-passed bill would:
Set firm deadlines for federal environmental reviews.
Cut the time to challenge a NEPA review from six years to 150 days, and limit courts to sending flawed reviews back to the agency rather than vacating them.
Let FERC permit transmission lines of 230 kV or more after a state has had a year to act. These siting provisions would not apply in ERCOT.
Exempt reconductoring within existing rights-of-way from NEPA review.
Require FERC to revise transmission pricing within 90 days so that new data centers cannot shift costs to other customers, and require them to post financial guarantees.
Supporters say the bill will speed construction and lower energy costs. Opponents have raised concerns about weaker environmental reviews, limits on judicial oversight and tribal consultation.
Speaker Mike Johnson has said he will try to pass the bill under suspension of the rules as early as the week after Thanksgiving, according to Heatmap. That procedure requires a two-thirds majority. Some House Democrats have argued for waiting until the new Congress convenes in January.
The bill is not law. The House must pass the identical text and the President must sign it. Agencies would then have to implement it, including FERC's 90-day data-center pricing revision.
Developer Takeaway
Underwrite projects against current law until the bill is enacted and implemented. Model both cases now, because several provisions bear directly on underwriting. A 150-day challenge window would change how long entitlement risk sits on a project. Mandatory data-center financial guarantees would change how much capital a large-load project needs before service. The reconductoring exemption favors sites served by existing corridors, the model Google is testing in Ohio this week (03).
02 | POLICY & GRID SECURITY
FERC Clears NIPSCO's Affiliate Power Purchases for Data-Center Load
On November 19, FERC authorized Northern Indiana Public Service Company (NIPSCO) to buy energy and capacity at market-based rates from its affiliate, NiSource Generation Company (GenCo), so it can serve rising load in its territory (Dockets ER26-3474-000 and ER26-3475-000).
The two power purchase agreements let NIPSCO serve data-center customers under special contracts approved by Indiana regulators. The first is Amazon. For Amazon, GenCo plans to build up to 3 GW: two 1.3 GW gas-fired plants and a 400 MW, four-hour battery. The GenCo structure, also used for Microsoft's northwest Indiana campus covered in Issue No. 09, is designed to keep the cost of serving hyperscale customers off NIPSCO's existing ratepayers.
FERC's order authorizes sales between affiliates. It does not approve or build the generation, which still requires permitting, equipment and construction.
Developer Takeaway
The utility's commercial structure is becoming as important as its physical capacity. Where a dedicated generation affiliate serves large loads, the service schedule depends on that affiliate's build program, not just on transmission. Diligence should cover both.
03 | POWER & GRID
Google Offers to Pay for Faster Transmission in Columbus
On November 19, Google and Ohio Power Company, an American Electric Power subsidiary, filed a joint proposal with the Public Utilities Commission of Ohio. Under it, Google would pay the $10.8 million incremental cost of installing advanced conductors on 15.5 miles of 50-year-old transmission lines in Columbus. Ohio Power had already planned to rebuild those lines.
Once installed, the upgrade would let 24 MW that Google has already contracted arrive about two years early. After a separate, planned 765 kV buildout in Central Ohio is complete, the corridor is expected to carry more than 700 MW of additional capacity. The companies say the work would also cut line losses and slightly reduce the transmission costs other customers pay. Google is also providing $1 million for lineworker training and manufacturing apprenticeships in Ohio.
The proposal needs approval from both the PUCO and the Ohio Power Siting Board. The upgrade is expected in service by late 2028, pending those approvals. The 700 MW depends on the 765 kV buildout, not on this project alone.
It builds on two earlier stories. One is the reconductoring approach DOE is funding in Virginia and West Virginia, covered in Issue No. 08. The other is AEP's push into customer-funded infrastructure, covered in Issue No. 11.
Developer Takeaway
Paying the incremental cost of an upgrade the utility already plans may be the fastest route to energization in constrained corridors. Powered-land diligence should ask which planned rebuilds sit near a site and what advanced conductors on them could add. The amount at stake is small relative to what earlier power is worth.
Winter Outlook Improves, but Extreme Cold Remains the Risk
NERC's 2026–2027 Winter Reliability Assessment, released November 18, finds the outlook improved because of resource additions, delayed retirements and better cold-weather generator performance. All assessment areas are expected to have adequate resources for normal winter peak load. On-peak capacity resources grew 26.2 GW, led by batteries and gas.
Extreme, wide-area cold could still cause supply shortfalls. Several areas face elevated risk to gas fuel supply during prolonged cold. Winter peak demand forecasts rose in 21 of 23 assessment areas, driven mainly by data centers and electrification. FERC staff presented their own winter assessment on November 19.
Developer Takeaway
Mission-critical facilities should be designed for the extreme case, not average grid availability. Fuel security, onsite storage and the ability to reduce load on instruction remain core design questions.
04 | DATA CENTER / MISSION CRITICAL
Data-Center Construction Starts Dip in the Third Quarter, Then Rebound
U.S. developers started construction on 8.4 GW of data-center capacity across 65 buildings in the third quarter, according to Cleanview. That was down 28% from a record 11.7 GW across 96 buildings in the second quarter. It was still 55% above the third quarter of 2025.
Starts rebounded to 4.6 GW in October, the second-largest month on record and nearly double October 2025. The largest included:
Nscale's Monarch campus in West Virginia, leased to Anthropic (720 MW)
Related Digital's Stargate Michigan campus, for Oracle and OpenAI (461 MW)
Crusoe's Abilene, Texas, campus, for Microsoft (450 MW)
Those three buildings alone account for about a third of October's total.
Cleanview counts a start when vertical construction begins, identified from satellite imagery. These figures are construction starts, not energized or operating capacity. Cleanview puts 58 GW under construction against 65 GW operating.
Developer Takeaway
Single buildings of 450 to 720 MW can swing a quarter's total, so read monthly figures with care. The pipeline remains large, but it is concentrated among projects that already have power, financing and equipment lined up.
05 | ENERGY INFRASTRUCTURE
Avantus Signs $3 Billion of Solar and Storage Contracts With PG&E
On November 17, Avantus announced 20-year power purchase agreements with Pacific Gas and Electric for Buttonbush 1A and 1B, the first phases of its Buttonbush Solar Center in western Kern County.
The two phases combine 800 MW of solar with 3,200 MWh of battery storage, an estimated $3 billion investment. Construction is expected to start in 2027, with commercial operation in 2029. Avantus plans to own and operate the projects as an independent power producer.
The projects will be built on water-stressed farmland. Avantus says this helps meet state groundwater requirements, gives participating farmers long-term lease income and leaves scarce water for other crops.
The agreements are subject to California Public Utilities Commission approval.
Developer Takeaway
Central Valley land where water policy is constraining agriculture is becoming a generation asset. The value depends on matching that land with transmission access and a creditworthy, long-term offtaker.
FERC Certificates Five Gas Projects, Including One Built Around a Power Plant
On November 19, FERC voted unanimously to approve five natural-gas projects:
Sabine Pass: a Stage 5 expansion of the LNG terminal in Louisiana.
Mountain Valley Pipeline: the MVP Boost project, adding 600,000 dekatherms per day mainly through compression.
Columbia Gas Transmission: an LNG storage facility in Sussex County, Virginia.
Forza Pipeline: about 36 miles of new pipeline carrying up to 750,000 dekatherms per day from the Delaware Basin toward Waha.
Texas Eastern: an extension of its Line 31 in Madison County, Mississippi.
The Line 31 expansion stands out for this audience. Its 125,000 dekatherms per day are fully contracted by Entergy Mississippi to supply its planned Traceview Advanced Power Station, with service sought by September 1, 2028.
A certificate authorizes construction subject to conditions. It is not a final investment decision or a construction start.
These approvals follow FERC's proposals to speed LNG and gas reviews, covered in Issue No. 08.
Developer Takeaway
Gas supply is being permitted around specific power plants. Where onsite or bridge generation is part of a plan, evaluate delivery capacity, pressure, firm contracts and air permits with the same rigor as the electrical connection.
06 | EQUIPMENT & SUPPLY CHAIN
RE+ Puts Storage and Onsite Generation in the Same System
Last week's RE+ conference in Las Vegas showed equipment makers designing integrated power systems for large computational loads.
LG Energy Solution showed its JF3 LINK grid-scale storage system, built with U.S.-made LFP batteries. LG says it delivers about 26% more energy per site than its previous products. LG also presented a concept that pairs sodium-ion batteries with solid-state transformers to respond to rapid swings in data-center load.
Trina Storage launched its Elementa Hybrid Genset on November 18. It combines gas generators from partner suppliers with Trina's battery storage under a single plant controller, for projects from 5 MW to 1 GW. It is aimed at sites that are grid-connected, grid-constrained, bridging to a grid connection or off-grid. Trina says configurations will be set project by project.
These are product launches and concepts, not field-proven deployments at scale.
Developer Takeaway
AI loads demand systems that can follow fast load swings without compromising power quality. Equipment choice, controls, protection and civil design now need to be settled together and early, and claims about integrated products should be tested against each site's own requirements.
New Solar Import Prices Take Effect December 4
New Section 232 measures on polysilicon and its derivatives apply to goods entered from 12:01 a.m. Eastern on December 4. Proclamation 11052, signed August 6, sets these minimum import prices:
Polysilicon: $21/kg
Ingots and wafers: $100/kg
Solar cells: $0.22/W
Solar modules: $0.38/W
Imports entered below the floor pay a duty equal to the difference. A separate 15% duty applies to ingots, wafers, cells and modules, but not to raw polysilicon. Treatment varies for some trading partners.
U.S. Customs and Border Protection opened test codes for importers on November 12. Since September, a Commerce rule has allowed it to restrict imports by companies found to be stockpiling before the deadline.
The minimum price is a floor for entry, not a delivered equipment price.
Developer Takeaway
Revisit module pricing, supplier commitments, tariff pass-through clauses in EPC contracts and contingencies before fixing construction budgets. Who bears import risk should be settled in the contract, not discovered at the port.
07 | CAPITAL & DEAL FLOW
FERC Authorizes DigitalBridge's Acquisition of ArcLight
On November 19, FERC authorized subsidiaries of DigitalBridge Group to acquire ArcLight Capital Holdings (Docket EC26-115-000).
The deal was announced in May. It is valued at up to $1.05 billion: a $650 million base price plus up to $400 million of contingent consideration. The companies say the combined platforms represent more than $150 billion of assets.
The deal was conditioned on SoftBank's acquisition of DigitalBridge, which SoftBank completed on September 30. PJM's market monitor opposed the transaction, arguing that the combined PJM generation would increase market power.
FERC's authorization is one of several regulatory approvals the merger agreement requires. Closing has not been announced.
Developer Takeaway
Capital is consolidating around platforms that can combine generation, grid access and digital infrastructure. Development teams with credible power positions may increasingly be acquisition targets, as well as financing partners.
Energy Vault Finances a Merchant Texas Battery
On November 23, Energy Vault closed $78 million of construction and bridge financing for its 150 MW / 300 MWh SOSA Energy Center in Madison County, Texas, an approximately $100 million project. The bridge will be repaid from an $80 million preferred equity investment already committed for completion. The lenders were not named.
Civil work is complete and the substation is installed. Energy Vault is self-performing EPC. The project targets commercial operation in the third quarter of 2027 and will initially run on a merchant basis in ERCOT North, with no offtake agreement in place.
In January, Energy Vault expected operation in the second quarter of 2027 and described a six-to-eight-year offtake as in advanced negotiations.
Developer Takeaway
Non-recourse capital is available for merchant storage, but it is being sized around the absence of contracted revenue. Expect lenders to scrutinize schedule and revenue assumptions closely, as this project's shift in both shows.
08 | THE INTERCONNECTION DESK
ERCOT
Batch Planning Continues; Batch Zero Remains Paused
ERCOT's November 19 Large Load Working Group covered three items:
Status of its voltage ride-through review for large computational loads in Batch Zero
A protocol revision, NOGRR289
An update on the large-load portal
An afternoon workshop on batch planning covered concepts for the batches after Batch Zero, bring-your-own-generation proposals, load-sponsored generation and large-load project changes.
Batch Zero, followed since Issue No. 01, remains paused. ERCOT's September Board update states that the study process and final classification have been paused since August 3. Energization of new data centers of 75 MW or more is paused until the verification, audit and community-impact review are complete. Both reports are due December 10.
Developer Implication
Work on later batches is design work, not a path to energization. Texas teams should not treat any interconnection arrangement as final while the pause continues.
PJM
Comment Deadlines Set on Ride-Through Rules
PJM's November 16 filings, the Lead in Issue No. 12, now have dockets.
Comments on the ride-through requirements for large computational loads (ER27-522) are due December 7. PJM asked for those requirements to take effect January 16, 2027.
For Fast Energization (ER27-531), PJM asked FERC for a 60-day comment period, to January 15, and an order within 120 days. If approved, the first application window would open in late November 2027, and the first cycle would finish in 2029.
Neither filing has been approved.
Developer Implication
Even on PJM's own schedule, Fast Energization would not deliver study results before 2029. Plan near-term PJM projects on the existing process.
CAISO
Large-Load Comments Due December 7
Comments on CAISO's large-load tariff amendment (ER27-506), covered in Issues No. 10 through No. 12, are due December 7. CAISO filed an amendment on November 18, with comments due December 9. It has requested a February 16, 2027 effective date. FERC has not acted.
Developer Implication
California large-load projects should review the filing now. The comment window is the last chance to shape requirements before FERC rules.
09 | ON OUR RADAR
Southern California Public Power Authority | November 25
The standalone energy-storage RFP closes.
Illinois Power Agency | November 30
Bids are due in the Fall 2026 Indexed REC RFP. It covers new utility-scale wind and solar, brownfield photovoltaic and hydropower projects.
U.S. House | As early as the week of November 30
A possible vote on the Senate-passed permitting bill (see 01). Under suspension of the rules, it would need two-thirds.
Section 232 solar import measures | December 4
Minimum import prices and the 15% duty take effect (see 06).
PJM and CAISO | December 7 and 9
Comments are due on PJM's ride-through filing and CAISO's large-load amendment (see 08).
ERCOT | December 10
The Batch Zero eligibility verification and community-impact reports are due.
Southern California Public Power Authority | December 16 and 30
For the Q3–Q4 Renewable Energy Resource and Energy Storage Solutions RFP, clarification questions are due December 16 and proposals December 30.
These solicitations are resource procurements. They seek project proposals, not engineering services.
THE INTERFACE VIEW
From Power Consumption to Power Participation
This week showed a change in the relationship between large electricity customers, utilities and capital.
Google is offering to pay for transmission upgrades. NIPSCO is serving data centers through a generation affiliate built for them. A new gas pipeline expansion is contracted to a single new power plant. DigitalBridge is moving to combine digital and power infrastructure investment. And Congress is close to changing how American infrastructure is permitted and paid for.
The common denominator is integration.
The next generation of successful developments will need more than land and a utility service request. They will need coordinated strategies for entitlement, generation, storage, transmission, engineering, equipment procurement and capital.
The competitive advantage will belong to those that bring these disciplines together early enough to turn development potential into infrastructure that can be built.
Interface Holdings and Development Firm