Infrastructure Intelligence No. 12: The New Rules of Power Access

Energy. Power. Development. Capital. | November 17, 2026 | Issue No. 12
THE WEEK IN INFRASTRUCTURE
Grid Operators Rewrite the Terms of Access
PJM asked FERC this week to cut its interconnection studies from about two years to one. It also asked FERC to require large data centers to stay connected through grid disturbances.
CAISO filed its own large-load tariff. ERCOT's Batch Zero process remains paused ahead of two reports due December 10.
Storage reached a milestone: cumulative U.S. installations passed 200 GWh. Capital continued to move into power-ready assets: Blackstone agreed to buy a 75% interest in $5 billion of AWS data-center shells, and Google signed for 50 MW of superhot geothermal power.
In the Senate, the permitting bill cleared a second procedural vote and is approaching a final vote.
The pattern is consistent. Access to power is being earned through readiness, technical performance and cost responsibility, not just requested.
01 | THE LEAD
PJM Moves to Halve Interconnection Study Timelines as Large-Load Scrutiny Intensifies
On November 16, PJM filed its Fast Energization proposal with FERC. The proposal would cut projected study timelines for new generation, and for transmission service to large electricity users, from about two years to one.
The filing came on the November 16 date for PJM's response in FERC's large-load show-cause proceeding, flagged in Issue No. 11.
The proposal would study generation and large loads together, removing duplicated steps. It would apply stricter readiness and financial requirements earlier, so speculative projects leave the process sooner.
It would also give states visibility into the transmission-upgrade costs that data centers drive, so they can decide how to bill large loads.
It would create new transmission services for large loads: one for loads with their own generation, one for flexible loads that can reduce their demand, and an interim service while network upgrades are being built.
PJM has asked FERC to set a 60-day comment period and to issue an order within 120 days.
This is a filing, not an approved process. Its timelines and benefits depend on FERC's order and on how PJM implements it.
Developer Takeaway
Faster studies help only projects that are ready for them. Earlier readiness and financial requirements mean site control, credible operating schedules and a power strategy will need to be in place at the start of the process, not assembled during it.
The new service options deserve attention. A large load that can bring its own generation or reduce demand on instruction may reach service sooner than one that needs firm service from day one.
Interconnection is becoming a front-end development discipline, not a late-stage utility coordination exercise.
02 | POLICY & GRID SECURITY
Permitting Bill Clears a Second Senate Vote
The Bipartisan American Affordability and Jobs Act moved closer to a final Senate vote this week.
On November 16, the Senate voted 70–27 to end debate on a managers' amendment that strengthens the bill's provisions on data centers and tribal sovereignty. A final Senate vote is expected before the Thanksgiving recess.
That follows the November 9 73–25 vote to begin debate, the Lead in Issue No. 11. The bill was introduced as S. 5653 and covered in Issue No. 07.
The legislation would accelerate federal reviews, improve permitting certainty and make large data centers responsible for more of the transmission costs they create.
Supporters say it would reduce delays and increase electricity supply. Opponents have raised concerns about environmental protections, judicial review and tribal consultation.
Neither vote was final passage. The Senate must still pass the bill, and the House must then pass the same text before it can be enacted. Its sponsors are seeking to complete it before the new Congress convenes in January.
Developer Takeaway
Developers should model how the bill would affect their schedules, permitting risk and large-load cost responsibility. Projects should still be underwritten against existing law until reform is enacted and implemented.
03 | POWER & GRID
U.S. Energy Storage Passes 200 GWh
The U.S. has passed 200 GWh of cumulative installed energy storage, according to the U.S. Energy Storage Market Outlook from SEIA and Benchmark Mineral Intelligence, released November 17 at RE+.
200+ GWh cumulative U.S. storage | 48.3 GWh installed January–September 2026 | 708 GWh projected cumulative by 2030
The industry installed 14.3 GWh in the third quarter, including 12.2 GWh of utility-scale storage. That was below the record second quarter. Year-to-date installations reached 48.3 GWh, 20% more than in the same period of 2025.
Texas led utility-scale installations through September, followed by Arizona and California.
SEIA and Benchmark raised their 2030 cumulative forecast by 3.7%, to 708 GWh. That is a forecast, not contracted or completed capacity.
Developer Takeaway
Storage is becoming core infrastructure for capacity adequacy, peak management and large-load integration. The opportunity now extends well beyond solar pairing, to standalone transmission-connected batteries and customer-sited systems.
PJM Accepts a Fourth Expedited Interconnection Project
On November 10, PJM accepted a 500 MW battery-storage project from Little Blue Solar LLC in Beaver County, Pennsylvania, in the ATSI zone, into its Expedited Interconnection Track.
That brings the track to four accepted projects, totaling about 2,615 MW: three storage facilities totaling 2,160 MW (including ENGIE's 860 MW and 800 MW projects) and a 455 MW upgrade at the Hunterstown gas plant. The first three were covered in Issue No. 07.
The projects target operation around mid-2029. Acceptance into the track is not a signed interconnection agreement, start of construction or final approval.
Developer Takeaway
Priority pathways are separating projects with real development readiness from those that remain speculative. It is notable that storage accounts for three of the four accepted projects.
04 | DATA CENTER / MISSION CRITICAL
Google Signs 50 MW Superhot Geothermal Agreement
On November 17, Quaise Energy announced that Google had signed a power purchase agreement for 50 MW from Project Obsidian in Central Oregon. Deliveries could begin as early as 2030, supporting Google's data centers in The Dalles.
It is Quaise's first commercial offtake agreement. Price and contract term were not disclosed.
The project would use superhot geothermal technology to provide continuous, carbon-free generation. It is under construction near Bend. Operating at commercial scale is still a development and technology milestone, not something the project has achieved.
Developer Takeaway
Hyperscalers are buying beyond intermittent renewables and conventional gas. Firm power with a credible long-term delivery profile may command increasing strategic value, even when first delivery is several years away.
Calibrant Finances Storage Serving a Hyperscale Customer in PJM
On November 10, Macquarie-backed Calibrant Energy closed a $145 million debt facility led by Investec, with Citi, Liberty Bank and Siemens Financial Services participating.
The facility refinances operating solar and storage assets and funds new construction. The portfolio includes a 120 MWh battery serving a hyperscale data-center customer in PJM.
The $145 million covers the whole portfolio. It should not be attributed to the battery project alone.
Developer Takeaway
Storage is entering the data-center capital stack as more than backup power. Well-designed systems can support demand management, interconnection strategy and operational flexibility, all of which this week's PJM filings make more valuable.
05 | ENERGY INFRASTRUCTURE
Masdar and Terra-Gen Complete $950 Million California Solar and Storage Complex
On November 13, Masdar marked the completion of the Lockhart Solar and Storage complex at Hinkley, in San Bernardino County, developed by Terra-Gen. Masdar and Igneo Infrastructure Partners jointly own Terra-Gen.
The $950 million complex combines 365 MW of solar with 173.7 MW of battery storage. It includes more than 925,000 solar modules and 248 battery enclosures. The final phase came online in July.
Masdar also restated its ambition to grow its U.S. portfolio to as much as 25 GW by 2030, supported by a planned $20 billion of further U.S. investment over the next decade. These are corporate objectives, not awarded contracts.
Developer Takeaway
The completion shows the scale at which integrated generation and storage is now being delivered. For developers and engineering firms, the Terra-Gen and Masdar pipeline may matter more than the completed Lockhart project.
Matrix Renewables Tests Automated Construction at 457 MW Texas Solar Project
On November 12, Matrix Renewables announced it is deploying Terabase Energy's Terafab V2 automated construction system on part of its 457 MWdc Tormes Solar project in Navarro County, Texas. Construction began in May.
SOLV Energy is the EPC partner. The system uses robotic module assembly, digital quality control and autonomous rovers to test whether utility-scale construction can run around the clock. It is a partial-site trial, not a project-wide method.
Developer Takeaway
Automation may increasingly shape site layout, construction sequencing, equipment standardization and engineering deliverables. It could reward developers that bring construction methodology into design earlier.
06 | EQUIPMENT & SUPPLY CHAIN
Grid Equipment Demand Stays Strong as Domestic Manufacturing Grows
On November 11, Siemens Energy reported fiscal 2026 results for the year ended September 30: revenue of €44.2 billion, a 12.4% profit margin before special items, €8.8 billion of pre-tax free cash flow and a record €164 billion order backlog. The results reflect strong demand for gas services and grid technologies.
On November 17, GE Vernova launched the HYpact-145g, a 145 kV compact switchgear that uses no SF₆ insulating gas. GE Vernova says it takes at least 50% less space than a conventional air-insulated substation. It was launched at a trade show in Cologne and is available to order now.
SEIA's supply-chain dashboard reports 75.3 GWdc of operational U.S. solar-module manufacturing capacity and 62.4 GWh of operational battery-cell capacity.
Nameplate manufacturing capacity does not necessarily mean product that is available, qualifies as domestic content or can be delivered now.
Developer Takeaway
Equipment specifications, factory capacity and delivery commitments increasingly shape project schedules and financial close. Early procurement coordination matters most for substations, transformers, electrical infrastructure and large battery installations. Compact designs may also open sites where substation footprint was the constraint.
07 | CAPITAL & DEAL FLOW
Blackstone Agrees $5 Billion AWS Data-Center Transaction
On November 16, Blackstone Digital Infrastructure Trust (BXDC) announced a definitive agreement to acquire a 75% interest in two joint ventures with AWS. The joint ventures own 13 newly built powered data-center shells on two AWS campuses, in northern Indiana and Mississippi. It is BXDC's first investment.
The transaction is valued at about $5 billion, at an initial capitalization rate of 7.0%.
AWS will keep a 25% interest and lease the entire portfolio on a triple-net basis for an initial 12 years, with extensions that could take the term to 32 years.
The agreement has been signed. Closing has not been announced.
Developer Takeaway
Institutional capital increasingly treats stabilized, power-ready data centers as long-duration infrastructure. Reliable electrical access, execution and creditworthy occupancy are central to valuation, and powered shells are now a financeable product in their own right.
Japanese Utility Capital Enters Operating PJM Battery Storage
On November 16, ArcLight Capital Partners and Elevate Infrastructure announced that Kansai Electric Power has agreed to acquire a minority interest in the operating 150 MW / 600 MWh Prospect Power battery in Rockingham County, Virginia.
The owners describe it as the largest operating standalone battery in PJM. It is Kansai's first battery-storage investment outside Japan.
The deal is an investment in an operating asset. It does not create a new engineering or construction procurement.
Developer Takeaway
Strategic and international capital buying into operating storage deepens the market for monetizing assets after construction. That in turn supports development platforms and construction financing.
08 | THE INTERCONNECTION DESK
PJM
Ride-Through Requirements Proposed for Large Computational Loads
In a separate November 16 filing, PJM proposed voltage and frequency ride-through requirements for a new category of large computational loads of 50 MW or more.
The proposal follows the July 22 event in northern Virginia, the Lead in Issue No. 03. In that event, nearly 3.9 GW of data-center load unexpectedly moved from grid power to onsite generation during a transmission disturbance. PJM called it the largest such load transfer in its history. PJM signaled this work at FERC's October technical conference, covered in Issue No. 09.
PJM has requested a January 16, 2027 effective date. FERC has not acted, and the requirements are not in effect.
Developer Implication
Large-load engineering packages may need more detailed electrical modeling, control coordination, protection design and evidence of ride-through performance.
CAISO
Large-Load Tariff Amendment Filed
CAISO filed its large-load tariff amendment on November 16 under FERC docket ER27-506. The filing follows the Board's October 28 approval, covered in Issues No. 10 and No. 11.
FERC approval and implementation are still to come.
Developer Implication
California large-load projects should track the technical requirements, cost allocation and how the new provisions may affect connection timing.
ERCOT
Large Load Working Group Meets Thursday; Batch Zero Remains Paused
ERCOT's Large Load Working Group meets November 19. The agenda covers ERCOT's large-load interconnection report, a status update on its voltage ride-through review for large computational loads in Batch Zero, and updates to the large-load portal.
Batch Zero, followed since Issue No. 01, remains paused. ERCOT's September Board update states that the study process and final classification have been paused since August 3. It also states that energization of new large-load data centers of 75 MW or more is paused until the verification, audit and community-impact review are complete. ERCOT's November 5 update to the PUCT kept December 10 as the target for both the eligibility verification and community-impact reports.
Developer Implication
Texas project teams should keep tracking reliability requirements and study procedures. They should not treat previously discussed interconnection arrangements as final while the pause continues.
09 | ON OUR RADAR
RE+ 2026 | Las Vegas | November 16–19
RE+ is under way at the Las Vegas Convention Center this week, with exhibits open from November 17. Large-scale storage, domestic manufacturing, utility interconnection, equipment supply and construction productivity are the conversations most relevant to near-term development strategy.
U.S. Senate | Before the Thanksgiving recess
Expected final Senate vote on the permitting bill (see 02). Passage would send it to the House. It would not make it law.
Southern California Public Power Authority | November 25 and December 30
SCPPA lists two developer-facing solicitations:
Standalone energy-storage RFP: closes November 25, 2026.
Q3–Q4 Renewable Energy Resource and Energy Storage Solutions RFP: closes December 30, 2026; clarification questions due December 16.
These are resource procurements. They seek project proposals, not engineering or consulting services.
Uniper | Powered industrial land
Uniper is repositioning former power-plant sites for data centers. It reports about 700 MW of secured grid capacity across roughly 10 sites in the UK, Germany, Sweden and the Netherlands, and the Financial Times reports it is close to a first deal.
The negotiations are reported, not completed development agreements.
Existing grid access can materially raise the development value of industrial and brownfield sites where a new connection would take years.
THE INTERFACE VIEW
Power Readiness Is Becoming the Defining Development Advantage
Three developments stand out this week. PJM is trying to accelerate the path to grid access. Grid operators are tightening the technical obligations of large electricity users. And investors continue to commit substantial capital to energy and digital infrastructure.
Together, these trends are changing how projects must be developed.
Land availability alone is no longer sufficient. Developers increasingly need a coordinated strategy covering utility service, generation, storage, transmission, equipment procurement, regulatory compliance and construction execution.
The strongest opportunities will be those that turn power availability into a credible schedule, a financeable project structure and infrastructure that can actually be delivered.